Julia Maley Park Well Treatment

Group of people planting a tree in a park.

Julia Maley Park Well Treatment

Julia Maley Park houses one of the city wells. This project is to build a water treatment facility for the well. This is one small step in helping  the City to provide clean water for the residents of Omak.

Projected Timeline

Week of March 17th

Site Work- Mobilization, TESP, Demolition, Cleanup, Rough grading, Underground piping, Underground electrical

Week of March 24th

Site Work- Roll off slab

Building- Excavate Footings, Pour building footings and slab, 

Week of April 7th

Site Work- Sewer

Resevoir- Reservoir pad, and Resevoir

Week of April 21st

Building- Walls

Week of May 5th

Building- Inside Piping

Week of May 19th

Site Work- Gravel Site

Building- Roofing

Week of May 26th

Building- Building electrical

Week of June 9th

Building- Paint

Week of June 14th

Building- Pipe Labels

Week of July 21st

Site- Set generator, Bollards concrete floor, System setting and start-up

Week of July 28th

Fencing

 

Due to unforeseen circumstances the completion date for the Water treatment Plant has been pushed back to mid September.